Bhopal Metro Rail News & Updates

2023-12-18
The structure work of Bhopal Metro is going on at a very fast pace. Work on 5 stations from Subhash Nagar to AIIMS has been completed, while work on DRMA Alkapuri and AIIMS metro stations is in the final stages. Whereas, as soon as the work of three stations is completed, Madhya Pradesh Metro Company will send a letter to the CMRS team of the Railways. After this, the CMRS team will hand over the safety certificate to the company after inspection. According to Metro officials, the interior work of Subhash Nagar, Kendriya Vidyalaya, Board Office, MP Nagar and Rani Kamalapati Railway Station has been completed. While the work of metro stations of DRM, Alkapuri and AIIMS is going on in the fina

2023-12-11
Two steel bridges for Bhopal Metro have been completed in Alwar, Rajasthan. Most of their major ports have been reached. These bridges have been designed like Delhi Metro. Whose total length will be 103 meters. If Metro Corporation officials are to be believed, the work will start in January after the approval from Railways. A bridge will pass over the railway track, which will be built at the DRM office intersection.

2023-10-03
मध्य प्रदेश के मुख्यमंत्री शिवराज सिंह चौहान आज 3 अक्टूबर, मंगलवार को राजधानी भोपाल मेट्रो रेल ट्रयल रन का हरी झंडी दिखाकर शुभारंभ करेंगे. भोपाल मेट्रो रेल परियोजना की स्वीकृत लागत 6941 करोड़ रुपए है. भोपाल में पहले चरण में लगभग 30.95 किलोमीटर पर मेट्रो रेल का काम चल रहा है. इसमें 16.77 किलोमीटर ऑरेंज लाइन- एम्स से करोंद चौराहा और 14.18 किलोमीटर ब्लू लाइन- भदभदा चौराहा से रत्नागिरी तिराहे को जोड़ेगी.

2023-09-25
The first rake of Bhopal Metro has reached the depot located in Subhash Nagar. The work of assembling the coach, which was going on since Tuesday, has also been completed. Now on Monday, it will be run on the test track located in the depot, after which it will reach the viaduct with the help of metro ramp. Before this, the work of charging the third rail has also started on the trial track, with the help of which the metro will be operated.

2023-09-22
Metro is running on your track in the capital Bhopal. Now, till September 25, the metro trial will start about 4 to 5 times at Subhashnagar depot, while the final trial run will take place in front of Chief Minister Shivraj Singh Chouhan. Metro will be packed inside the package, brothels will run on the tracks again. After this the final final run will be done. Eight stations have been built in the capital Bhopal for Metro, these include AIIMS Hospital, Alkapuri, D Fail Office, Rani Kamalapati Station, Sargam Talkies, DB Mall, Christian School and Subhashnagar Station.

2023-09-11
Three coaches of the Bhopal Metro train with inbuilt engines left for Bhopal after being loaded onto a heavy transport vehicle at the Gujarat-based manufacturing unit on the intervening night of Saturday and Sunday. Heavy vehicles carrying metro coaches will reach Bhopal in 10 days. After reaching the city, the metro coaches will be dropped at Subhash Nagar depot. Let us tell you that the trial of the metro train is likely to happen around September 30.

2023-09-02
The trial run of Bhopal Metro is to be held in the last week of this month, for which the first rake of Metro will leave from Savli in Gujarat on 6th September. It will be placed on three trolleys and brought to Bhopal. Before this, a mock trial of the route through which the Metro has to reach Bhopal will be done. During this, the green signal will be shown only after checking the width of the route, weight of train and trolley, bend in the route and other technical checks.

2023-08-31
The first metro train for the Bhopal-Indore Metro project was handed over by Alstom to Madhya Pradesh Metro Rail Corporation (MPMRCL) on August 31. The train will be sent to Indore and is expected to be operational by April 2024. A mock-up car was unveiled by the Chief Minister of Madhya Pradesh on August 26 at the Smart City Park in Bhopal. The second train is expected to reach Bhopal by September 20.

2023-08-28
Before the trial run of Bhopal Metro, a trolley run was done on the track on Saturday, in which the Bhopal Metro track has passed, that is, the track is ready for the trial run of Metro. This trolley run was done between Subhash Nagar to Rani Kamlapati Railway Station (RKMP). Actually one month is left for the trial run of Metro.

2023-07-12
A review meeting was held on Monday regarding the progress of construction works in view of the target of Metro trial run of the priority corridor. 56 days are to go before the proposed trial run of Bhopal Metro in the 4-km long priority corridor. Coaches are set to arrive in August and main concern remains the construction work at metro depot at Subhash Nagar.

2023-07-04
Metro is to be operated in the 14 kilometer elevated route from Ratnagiri Tiroh to Bhadbhada square in the capital. In this, Rs 1122 crore will be spent on elevated corridors, 13 metro stations, rolling stock and other construction works. This project will be completed by the year 2026.